Architect says project 'moving along'

Rowynn Ricks

Things are “moving along” at Crystal Beach Park.

Architect Jim Hasenbeck provided members of the Woodward Parks and Beautification Board with this update during their monthly meeting Tuesday morning.

As the construction on phase one of the arena project continues, Hasenbeck noted that workers are in the process of completing the box seating areas and pouring concrete for the concession areas under the grandstands.

The contractor was even able to find a special machine with a 150-foot telescopic arm, which will allow the workers to simply pour the concrete where they need it under the grandstands, instead of having to use wheelbarrows to haul concrete back and forth, he said.

Besides the ongoing activity at the arena, Hasenbeck said “notice to proceed has been given to the contractor for the baseball fields.”

“Soon you’ll start seeing a convoy of trucks as they raise the level of the fields,” he said, noting that the objective is to have the fields raised to the proper level and sod in place and irrigated by July 31.

In addition, the aquatics center project will go to bid in the next couple of weeks, Hasenbeck said.

After that, he said the next two major projects will be renovating parking and landscaping areas and installing a new water line in the park.

But while progress is being made, Hasenbeck admitted that the project is a little behind schedule.

He also noted that rising construction prices may have an impact on the number of renovation projects that are completed at the park within the original $25 million budget, but he couldn’t say what the exact impact will be.

“Prices are higher,” he said. “But what that means for the overall project, who knows.”

However, Hasenbeck reminded the board that his team “intend(s) to build as much as we can at a quality level.”

“We have a commitment to doing quality stuff,” he said, noting that “we also have a commitment to do work in all four quadrants (park, sports, arena, golf course).”

print this story  



Photos


A worker digs out a trench for concrete footings at Crystal Beach Arena Tuesday afternoon. Photo by Rowynn Ricks/Woodward News (Click for larger image)

Zillow
monster
autoconx
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Premier Guide

Premium Jobs

SALES
LOCAL
SALESPERSON WANTED
Full time sales person wanted for established company (31 years). If you are a worke
...>MORE

Service Technician
Solitaire of Woodward is taking applications for
Service
Technician
Job Requirements:
Drivers Licen
...>MORE

NOW HIRING TECHNICIAN
Immediate opening in Woodward, OK for Appliance/Refrigeration/HVAC
Repair Technician
Up to $1500 sign-on bon
...>MORE

BONUS!
FT RN’s $7500 Bonus
LPN’s $5000 BONUS

Great Plains Regional’s & Elk City’s explosive growth means great
...>MORE

See all ads

Premium Autos

2002 CONVERTIBLE
Thunderbird with hardtop & stand, canary yellow, 43,000 miles, two tone leather interior. $16,900. 580-334-6397....>MORE

See all ads

Premium Homes

WE CAN HAVE YOUR $8000 tax credit in 2 weeks!
ZERO DOWN!
Guaranteed approval if you own land or can use family land! Only 2% down on all land-home purchases! ...>MORE

Lancer Homes MUST be liquidated!!
Elk City Quality Homes is changing back to Solitaire Homes. All Remaining Lancer Homes MUST be liquidated!!! No
...>MORE

See all ads


 

Community Newspaper Holdings, Inc.CNHI Classified Advertising NetworkCNHI News Service
Associated Press content © 2009. All rights reserved. AP content may not be published, broadcast, rewritten or redistributed.
Our site is powered by Zope and our Internet Yellow Pages site is powered by PremierGuide.
Some parts of our site may require you to download the Flash Player Plugin.
View our Privacy Policy
Advertiser index